A bid bond is a surety bond a contractor submits with a bid. It promises the owner that if the bid is accepted, the contractor will sign the contract and provide the performance and payment bonds the job requires. If the contractor walks away instead, the surety pays the owner its loss, up to the amount of the bond. Public work almost always asks for one, and some private owners do too.
How a bid bond works
Three parties sign a bid bond:
- The principal: the contractor submitting the bid.
- The obligee: the owner or agency asking for bids.
- The surety: the bonding company that backs the contractor's promise.
If you win and sign the contract with its bonds, the bid bond has done its job and is released. If you win and refuse to sign, the owner can claim on the bond. On the AIA A310 form, used on many private and local jobs, the surety pays the difference between your bid and the larger amount the owner has to pay another bidder, up to the bond amount. The surety then looks to you for repayment under the indemnity agreement you signed when you set up your bonding.
How much is a bid bond?
The bid documents set the amount, usually as a percentage of your bid:
- Federal work: the bid guarantee must be at least 20% of the bid price, up to $3 million, under the Federal Acquisition Regulation (FAR Part 28).
- State and local work: many states require at least 5% of the bid, including Georgia, Kentucky, New Mexico and Rhode Island, and some set 10%. Cities, counties and school districts set their own in the invitation to bid.
That percentage is the bond's penal sum: the most the surety can owe. It is not what the bond costs you.
What a bid bond costs
Many sureties issue bid bonds at little or no charge to contractors they already bond, because the real underwriting is for the performance and payment bonds that follow. The premium comes with those bonds if you win, often quoted around 1% to 3% of the contract amount, depending on the size of the job and the strength of your company. Ask your surety agent how they charge before bid day.
Bid bond vs. performance bond vs. payment bond
| Bond | When you provide it | What it guarantees | Usual amount |
|---|---|---|---|
| Bid bond | With the bid | You will sign the contract and provide the other bonds | A percentage of the bid: at least 20% on federal work, often 5% or 10% on state work |
| Performance bond | When the contract is signed | You will finish the work as the contract says | Often 100% of the contract; 100% on federal work unless the contracting officer sets less |
| Payment bond | When the contract is signed | Your subcontractors and suppliers get paid | Often 100% of the contract on public work |
On federal construction, the Miller Act requires performance and payment bonds on contracts over $150,000, and most states have similar laws, often called "Little Miller Acts," for state and local projects.
Alternatives to a bid bond
Many owners accept other bid security instead of a bond. On federal work, FAR Part 28 allows United States bonds or notes, certified or cashier's checks, bank drafts, money orders, cash, or an irrevocable letter of credit. A check or letter of credit ties up your cash or your credit line until the bids are decided, which is why most contractors use a bond.
How to get a bid bond
- Find a surety agent who writes construction bonds. Start well before the bid you need it for; setting up a bond program takes time.
- Expect underwriting. Sureties look at character, capacity and capital: your track record, your ability to do the work, and your finances.
- Prepare the paperwork: company and personal financial statements, a schedule of work in progress, résumés of key people, and the bid documents for the job.
- Get your bond line: the largest single job and the total work the surety will back. Stay inside it, and grow it as your company grows.
Small contractors who cannot qualify yet can look at the SBA's Surety Bond Guarantee program, which backs bid, performance and payment bonds for eligible small businesses on contracts up to $9 million, or up to $14 million on federal contracts with the contracting officer's certification.
Bond mistakes that get a bid rejected
- The wrong form. Federal bids require Standard Form 24. Courts and the GAO have found bids nonresponsive when bidders used the AIA A310 instead.
- The wrong amount, or a percentage the documents don't allow.
- The wrong names: the obligee, the project or the bid date doesn't match the solicitation.
- Missing signatures, or no power of attorney from the surety's agent.
- An unacceptable surety. Federal work requires a surety on the Treasury's list of approved companies, Department of the Treasury Circular 570.
Bonds are one part of the bid package. Our guide on how to bid a construction job covers the rest, and the free construction estimate template includes a bid form.
How BidMe helps
A bond backs your price, so the price has to be right. BidMe prices public and private bids from your plans, trade by trade, at local or prevailing wage, with alternates and unit prices ready for the bid form. See commercial construction estimating or pricing: from $199 for residential and $399 for commercial.
Questions contractors ask
What is a bid bond in simple terms?
A promise from a surety company that a contractor who wins a bid will sign the contract and provide the required bonds. If the contractor backs out, the surety pays the owner its loss, up to the bond amount.
How much does a bid bond cost?
Often little or nothing, when your surety already bonds you. The premium comes with the performance and payment bonds if you win, commonly quoted around 1% to 3% of the contract.
What percentage is a bid bond?
Whatever the bid documents say. Federal work requires at least 20% of the bid price, up to $3 million. Many states require at least 5%, and some 10%.
What happens if I win and do not sign the contract?
The owner can claim on the bid bond. The surety pays the owner its loss up to the bond amount, then seeks repayment from you under your indemnity agreement.
What is the difference between a bid bond and a performance bond?
A bid bond backs your promise to sign the contract if you win. A performance bond, provided when you sign, backs your promise to finish the work.