How to Bid a Construction Job, Step by Step

The whole bidding process for contractors, from finding bids worth chasing to the bid form: reading the documents, pricing the work, sub quotes, bid bonds, and the mistakes that get a bid thrown out.

By the BidMe estimating team,

To bid a construction job, find bids that fit your work and your capacity, read every bid document and addendum, take off and price the work, collect and compare sub quotes, add general conditions and markups, arrange any bid bond, then fill in the bid form exactly as written and deliver it before the deadline. Most lost bids are lost on scope or paperwork, not on the price.

1. Find bids worth chasing

Bids come from three places:

  • General contractors who invite subs they know. A good relationship is worth more than any bid list.
  • Plan rooms and bid services that list private and public projects, with drawings to download.
  • Public agencies: federal work is posted on SAM.gov, and states, cities, school districts and transit agencies post on their own procurement sites.

2. Decide go or no-go

Every bid costs estimating time, so choose. Bid the job if most of these are true:

  • It is your kind of work, at a size your crews and cash flow can carry.
  • There is time to price it properly before the due date.
  • Your bonding capacity covers it, if bonds are required.
  • You know the GC or owner, or their payment record is good.
  • The risk is priced in the documents: schedule, liquidated damages, retainage and site conditions.

3. Read the bid documents, all of them

DocumentWhat to look for
Invitation to bidDue date and time, where to deliver, pre-bid meeting, bonds
Instructions to biddersFormat, what must be attached, how bids are opened, how long they stay valid
Bid formBase bid, alternates, unit prices and allowances, exactly as they must be filled
Drawings and specsScope, materials, the details that change price
AddendaEvery change since the set was issued; most bid forms ask you to list them
General and supplementary conditionsPayment terms, retainage, insurance, schedule and damages

Go to the pre-bid meeting and walk the site when you can. Send questions as RFIs before the deadline the documents give, and read every answer that comes back as an addendum.

4. Take off and price the work

Measure every quantity from the drawings, organized by CSI division, and price it: material from current supplier quotes with tax, labor as hours per unit times your burdened wage, and equipment. Our guide on how to estimate construction costs walks through the method. Public work often requires prevailing wage: federally funded construction contracts over $2,000 fall under the Davis-Bacon Act, and most states have their own prevailing wage laws.

5. Get and compare sub quotes

If you are the GC, send each trade a clear scope, then line up the quotes side by side. Quotes rarely cover the same scope, so check each one against your own takeoff of that trade, and add what a low quote left out before you carry it. A sub that excludes something you did not catch is not the low number.

6. Add general conditions, markups and contingency

Price general conditions from the schedule: supervision for the months the job runs, temporary facilities, cleanup, permits and insurance. Then add overhead, profit and a contingency that fits the risk. Know your overhead as a share of your revenue, so the markup covers it on every job.

7. Bonds and insurance

Public jobs usually ask for a bid bond, which promises that the low bidder will sign the contract. On federal work the bid guarantee must be at least 20% of the bid price, up to $3 million, under FAR 28.101-2; states and cities set their own amounts. The winner then furnishes a performance bond and a payment bond: the Miller Act requires both on federal construction contracts over $150,000, and most states have similar laws for state work. Ask your surety early, and check that your insurance meets the limits in the documents. Our guide to bid bonds explains the amounts, the costs and the mistakes that get a bid rejected.

8. Fill in the bid form exactly

  • Write the base bid where the form asks, in words and figures if it asks for both.
  • Price every alternate and unit price the form lists. A blank can make the bid nonresponsive.
  • Acknowledge every addendum by number.
  • Sign it, attach the bond and anything else the instructions require, and seal it as instructed.
  • Deliver it before the deadline, in the place or portal named. Late bids on public work are usually rejected without being opened.

Our free construction estimate template includes a bid form sheet that carries the base bid from your estimate.

9. After the bid

Public bids are usually opened and read aloud, and the results posted. Get the bid tabulation, see where you landed, and ask for a debrief on jobs you lost. Track your hit rate by job type, so you bid more of the work you win.

How BidMe helps

BidMe does steps 4 to 6 for you: a takeoff and priced estimate from your plans, organized by CSI division, in 24 to 48 hours, with a bid summary and a proposal in your name. See our general contractor estimating and construction takeoff services, or pricing: from $199 for residential and $399 for commercial.

Questions contractors ask

What should a construction bid include?

The base bid, every alternate and unit price the form asks for, the addenda you received, your inclusions, exclusions and clarifications, how long the price is valid, and any bond, insurance certificate or form the instructions require.

How do I bid government construction jobs?

Register where the agency posts work, such as SAM.gov for federal contracts, read the solicitation closely, price prevailing wage if it applies, arrange the bid bond, and submit exactly as the instructions say before the deadline.

What is a bid bond?

A surety bond that guarantees the low bidder will sign the contract and furnish the required bonds. On federal work it must be at least 20% of the bid price, up to $3 million; states and cities set their own amounts.

How long is a construction bid valid?

As long as the bid documents say. If they do not say, state your own validity period on the bid, so a price from months ago cannot be held against you.