How to Estimate a Painting Job, Step by Step (Commercial)

How painting contractors price a commercial job from the drawings: the finish schedule and paint specs first, then surfaces by system, gallons from spread rates, labor by surface, and the access and prep that decide the margin.

By the BidMe estimating team,

To estimate a commercial painting job, start with the finish schedule and the paint specs, then take off every surface by its paint system: walls and ceilings in square feet, doors and frames counted each, trim and railings by length, exteriors by elevation. Work out the gallons from each product's spread rate and the number of coats. Price labor by surface, add lifts, scaffolds, prep and protection, then overhead and profit.

Read the finish schedule and the paint specs first

The finish schedule says which rooms get paint and on which surfaces. The paint specs say what goes on them. Read both before you measure:

  • The room finish schedule and legend: wall, ceiling and base finishes for every room, and accent colors.
  • The paint specs: Division 09 91 00 (painting), split into 09 91 13 for exteriors and 09 91 23 for interiors, and 09 96 00 for high-performance coatings. They list each system: the substrate, the primer, the finish coats and the sheen.
  • The door and frame schedule: how many doors and frames, and which are factory-finished and which you paint.
  • The reflected ceiling plans and sections: exposed ceilings, ductwork and steel that get paint, and the ceiling heights that decide access.

A system is the unit you price. Gypsum board with a primer and two coats of eggshell is one system; hollow metal frames with a rust-inhibiting primer and two coats of semi-gloss is another. Two walls in the same room can be on different systems.

Take off every surface by system

SurfaceHow to measure it
WallsSquare feet by room and system
CeilingsSquare feet by room, with heights noted for access
DoorsCounted each, by type, both faces
FramesCounted each, by type
Trim, base and railingsLinear feet by type
Exposed structureSquare feet of deck, joists and ductwork, when the specs call for paint
ExteriorsSquare feet by elevation and substrate: siding, stucco, block, metal
Special coatingsEpoxy floors and high-performance coatings, by area and system

Measure room by room, so you can check each room against the finish schedule later. Keep accent walls on their own lines: a second color means its own cut-in.

Openings

The painting industry's measuring standard, the Painting Contractors Association's P10, leaves small openings in the area. Only openings of 100 square feet or more, or floor-to-ceiling openings wider than 5 feet, come out. Doors and windows of ordinary size stay in. Count them anyway: doors and frames are painted and priced on their own lines.

From square feet to gallons

Gallons for each system come from three numbers: the area, the number of coats and the spread rate on the product data sheet.

  • Gallons = area x coats ÷ spread rate, plus loss.
  • Commercial interior wall paints such as Sherwin-Williams ProMar 200 and Benjamin Moore Ultra Spec 500 are rated 350 to 400 square feet per gallon per coat on smooth surfaces, and their drywall primers the same.
  • Rough and porous surfaces take far more. Sherwin-Williams rates its Loxon masonry primer at 200 to 320 square feet per gallon on smooth surfaces and about 80 on rough stucco. Use the rate on the data sheet for the surface you have.
  • Add a loss allowance for what stays in trays, rollers and pails. Spraying loses more than rolling.

A worked example: a classroom wing with 12,000 square feet of wall, two coats at 350 square feet per gallon and 10% loss, needs 12,000 x 2 x 1.1 ÷ 350 = about 75.4 gallons. Round up to 76: fifteen 5-gallon pails and one gallon. If the walls are new drywall, add one coat of primer: 12,000 x 1.1 ÷ 350 = about 38 gallons.

The free paint calculator runs this math for a few rooms at a time.

Price labor by surface

Labor is where a painting bid is won or lost. Price it surface by surface, because each one moves at its own pace:

  • Open walls roll fastest. Cutting in at ceilings, corners and accent colors is slower per foot.
  • Doors and frames are priced each, by type, because a panel door takes longer than a flush one.
  • Trim, base and railings are priced by the linear foot.
  • Ceilings are slower than walls, and high ceilings slower still.
  • Exposed structure and ductwork are usually sprayed, with masking first.

For each surface, hours equal the quantity divided by your production rate. Your own crew's history is the best source for those rates. Multiply the hours by a burdened wage: the hourly wage plus payroll taxes, workers' compensation and benefits.

Public work often requires prevailing wage. Federally funded construction contracts over $2,000 fall under the Davis-Bacon Act, and many states have their own laws. Use the wage determination for the county and the painter classification, and say in the estimate which one you used.

Access, prep and protection

These lines are easy to leave out and expensive to absorb:

  • Access: scissor or boom lifts for gyms, lobbies and atriums; scaffolds or lifts for exteriors. Price the rental for the weeks you need it, plus delivery.
  • Prep: patching, sanding and caulking on new work; washing, scraping and spot priming on repaints. A dark-to-light color change usually needs a primer or an extra coat.
  • Protection: masking, floor protection and plastic in finished or occupied spaces.
  • Phasing: occupied schools and offices often work in phases, after hours or over summer break. Each phase can mean another mobilization.
  • Touch-up: a punch list after the other trades finish.

Overhead, profit and the bid

Add sales tax on material, then the job's supervision, then overhead and profit. List alternates on their own lines, and write down what you excluded, such as wallcovering, specialty coatings, or repairs to damage by other trades. A clear exclusions list protects the number you bid. Our guide to estimating a construction project covers markups and the final checks in more detail.

What gets missed most

  • Door and frame counts on a large school or office.
  • Both faces of every door.
  • Accent walls and second colors that each need their own cut-in.
  • Exposed ceilings, ductwork and steel in open areas.
  • Lifts in tall spaces, and scaffolds on exteriors.
  • Prep on repaints, and primer under a color change.
  • Extra mobilizations on phased work.

How BidMe handles painting

BidMe takes off every painted surface room by room and prices each one with the coats and products the specs name, at local wages or the prevailing wage the job requires. You get a live estimate in 3D and on your plans, an Excel workbook with every room, surface, gallon and labor hour, and marked-up plans. Read more about our painting estimating service, or see pricing: residential estimates start at $199 and commercial at $399.

Questions contractors ask

How do I work out how much paint a commercial job needs?

For each system, multiply the area by the number of coats, divide by the spread rate on the product data sheet, and add a loss allowance. Commercial wall paints are commonly rated 350 to 400 square feet per gallon on smooth surfaces, and far less on rough masonry and stucco.

Do painting estimators deduct doors and windows?

Under the Painting Contractors Association's P10 standard, small openings stay in. Only openings of 100 square feet or more, or floor-to-ceiling openings wider than 5 feet, are deducted.

How should doors and frames be priced?

Count them each, by type, and price both faces of every door. Leave out factory-finished doors and frames, which the door schedule usually marks.

When does a painting job need prevailing wage?

When the contract says so. Federally funded construction contracts over $2,000 fall under the Davis-Bacon Act, and many states have their own prevailing wage laws for public work. Use the wage determination for the county and trade.