To estimate drywall, measure every wall and ceiling by its wall type, multiply length by height for each face that gets board, and add ceilings, soffits and bulkheads. Turn the square feet into sheets with 10 to 15% waste. Screws, tape and joint compound follow from the board area. Price labor in two parts, hanging and finishing, because the finish level decides much of the finishing time.
Start with the wall types, not the floor plan
A floor plan shows where the walls are. The wall types say what each wall is made of, and that is what you price. Before you measure, read:
- The partition schedule and wall-type details: board type, thickness and layers on each face, stud size, gauge and spacing, and the fire rating.
- The sections: whether each wall stops at the ceiling or runs to the deck above. A wall that runs to the deck can be several feet taller than one that stops at the ceiling.
- The reflected ceiling plan: hard-lid ceilings, soffits and bulkheads, which are priced apart from walls.
- The specs: Division 09 21 16 (gypsum board assemblies), 09 22 16 (non-structural metal framing) and 09 29 00 (gypsum board) set the products, the finish level and the accessories.
Give each wall type its own color and measure the plans one type at a time. That way every square foot in the estimate traces back to a type and a sheet.
Measure walls and ceilings
| Item | How to measure it |
|---|---|
| Walls | Length times height for each wall type, once for each face that gets board |
| Heights | From the sections: to the ceiling or to the deck above |
| Layers | Multiply by the layers on each face; rated walls often take two |
| Ceilings | Length times width for each room with a hard-lid ceiling |
| Soffits and bulkheads | The bottom and both sides, measured on their own |
| Openings | Leave small ones in for material; take out large ones |
Openings are a judgment call. For a materials list, many crews leave doors and windows in: the board runs over a small opening and is cut out, so the sheet is bought anyway. Take out large openings such as storefronts and wide cased openings.
A worked example
One room, 12 by 14 feet, with 9-foot walls and a drywall ceiling:
- Walls: the perimeter is 52 feet, times 9 feet, so 468 square feet.
- Ceiling: 12 times 14, so 168 square feet.
- Board: 636 square feet. With 10% waste, 700 square feet.
- Sheets: 22 sheets of 4 x 8 (32 square feet each), or 15 sheets of 4 x 12 (48 square feet each).
The free drywall calculator does this math for any number of rooms.
Pick the right board for each wall
| Board | Where it goes |
|---|---|
| Regular 1/2 inch | Walls and ceilings in most rooms |
| 5/8 inch Type X | Fire-rated walls and ceilings, exactly as the listed assembly requires |
| Moisture- and mold-resistant | Behind tile and in damp rooms, but not where it gets direct water or constant high humidity |
| Abuse- or impact-resistant | Corridors, schools and other walls that take knocks |
| Shaft liner | Shaft walls at elevators, stairs and chases |
In a house with an attached garage, the International Residential Code (Table R302.6) calls for 1/2-inch board on the garage side of the wall it shares with the house, and 5/8-inch Type X on the garage ceiling when there are rooms above. Check the code edition your jurisdiction has adopted.
From square feet to materials
Once you have the board area, the rest of the material follows from published coverage:
| Item | Per 1,000 SF of board | Source |
|---|---|---|
| Screws on walls, 16 inches apart | About 750 (24 per 4 x 8 sheet) | National Gypsum coverage table |
| Screws on ceilings, 12 inches apart | About 1,000 (32 per 4 x 8 sheet) | Spacing from IRC Table R702.3.5 |
| Paper joint tape | About 370 feet | USG |
| Ready-mixed all-purpose compound | 9 to 10 gallons, about two 4.5-gallon pails | USG, National Gypsum |
| Waste on board | 10 to 15% | National Gypsum, Georgia-Pacific |
For the 12 by 14 room above, that is about 519 screws, 236 feet of tape and 6 gallons of compound, so two pails.
Add the accessories by length: corner bead on every outside corner, trim bead where board meets another material, and control joints where the specs call for them. If framing is in your scope, count studs by spacing for each wall type (the wall length divided by the spacing, plus one), and add extra studs at corners, openings and intersections. Track runs top and bottom. Add headers, deflection track at deck heads, and backing for cabinets, grab bars and wall-hung equipment.
The finish level drives finishing labor
The Gypsum Association's GA-214 defines six finish levels. The specs name the one each area needs:
- Level 0 and 1: no finish, or tape set in compound only, for areas above ceilings and out of sight.
- Level 2: tape and one thin coat, for garages, storage and walls that will get tile.
- Level 3: one more coat on the joints, for walls that will get a heavy texture.
- Level 4: two coats on flat joints and three on screws, the usual finish under flat paint and light texture.
- Level 5: Level 4 plus a skim coat over the whole surface, for gloss paint or strong side light.
A Level 5 wall takes far more time and compound than a Level 4 wall of the same size. Price finishing by finish level, not as one rate for the job.
Pricing labor
Split labor into hanging and finishing, and price each from production rates: hours equal the quantity divided by how much a crew does in an hour. Your own crew's history is the best source. Published labor units are the next best. Multiply the hours by a burdened wage: the hourly wage plus payroll taxes, workers' compensation and benefits.
Then adjust for what slows a crew down:
- Ceilings and soffits hang slower than walls.
- Walls above the reach of a crew on the floor need lifts or scaffolds, which are priced as equipment too.
- Small rooms, closets and stairwells have more cuts per sheet.
- Curved walls, two-layer walls and Level 5 areas take extra time.
Public jobs often require prevailing wage. Federally funded construction contracts over $2,000 fall under the Davis-Bacon Act, and many states have their own prevailing wage laws. Use the wage determination for the county and the trade, and name it in the estimate.
What gets missed most
- Walls that run past the ceiling to the deck, priced at ceiling height.
- The second layer on two-layer rated walls.
- Both faces of a wall, counted once.
- Soffits, bulkheads and furr-downs above cabinets.
- Shaft walls at stairs, elevators and mechanical chases.
- Backing and blocking for wall-hung items.
- Patching after other trades on renovation work.
- Lifts and scaffolds for tall walls and lobbies.
How BidMe handles drywall
BidMe measures drywall by wall type, floor by floor, with board, framing, finishing and labor on their own lines at the rates of the area where the job will be built. You get a live estimate in 3D and on your plans, an Excel workbook with the formulas left open, and marked-up plans. Read more about our drywall estimating service, or see pricing: residential estimates start at $199 and commercial at $399.
Questions contractors ask
How do I work out how many sheets of drywall I need?
Add up the square feet of board for walls and ceilings, add 10 to 15% for waste, and divide by the square feet in one sheet: 32 for a 4 x 8, 48 for a 4 x 12. Round up.
How much joint compound does one sheet of drywall take?
About 0.3 gallons of ready-mixed all-purpose compound for a 4 x 8 sheet, from the 9 to 10 gallons per 1,000 square feet that USG and National Gypsum publish for taping and finishing. A Level 5 skim coat takes more.
Should I take doors and windows out of a drywall takeoff?
For material, small openings are usually left in, because the board runs over them and is cut out. Take out large openings such as storefronts. For labor, count the openings, since every one adds cuts and corner bead.
Do you price drywall per sheet or per square foot?
Material is bought by the sheet, but most estimates price by the square foot of board, with hanging and finishing as separate lines. That keeps labor tied to the finish level and the height of each area.