A 3D takeoff is a quantity takeoff measured from a three-dimensional model of the building instead of from flat plan sheets. Every wall, slab, pipe, wire and fixture in the model has a size, a type and a location, so its square feet, cubic yards, linear feet or count come straight from the model. The quantities still need checking, waste, the items a model leaves out, and pricing before they become a bid.
A takeoff, measured from a model
Every takeoff answers the same question: how much of each thing does this job need? In a 2D takeoff, an estimator measures that from the sheets, one sheet at a time, and the heights come from sections and notes. In a 3D takeoff, the building already exists as objects, at their real heights and slopes, and the quantities are read from those objects.
That changes three things:
- Heights and slopes are built in. A wall that runs to the deck is measured at its real height. A roof plane is measured at its pitch, not its footprint.
- Every quantity has a place. You can point at an object and see what it is and where it sits, which is how you check a number.
- Overlaps show. Two objects in the same place look wrong in 3D, even when the numbers in a table look normal.
What a 3D takeoff gives each trade
| Trade | What the model measures |
|---|---|
| Concrete | Cubic yards of footings, walls and slabs; square feet of formwork; linear feet of edges |
| Framing | Wall lengths and heights by type, openings, headers, sheathing area |
| Drywall | Board area by wall type and face, ceilings, soffits, heights to the deck |
| Roofing | Each plane at its slope, ridges, hips, valleys, eaves and rakes |
| Electrical | Devices and fixtures counted, every circuit run in feet, from box to panel |
| Plumbing and HVAC | Pipe and duct by size and length, fittings, fixtures and equipment |
| Painting | Wall, ceiling and trim surfaces by room and system |
| Exterior finishes | Stucco, siding and masonry faces by elevation, gables included |
The model gives the measured quantity. The estimator still decides how it is bought and installed: sheets instead of square feet, coils instead of feet, plus waste.
How a 3D takeoff is done
- Get or build the model. On large projects the design team may release a BIM model, often from Revit. On most jobs there is only a PDF set, so the model is built from the 2D plans. We explain that in 3D estimating from PDF plans.
- Check the model before trusting it. A model is only as complete as the people who built it. Compare it with the sheets: wall types, heights, door and fixture counts, the schedules.
- Read the quantities by trade. Group them the way the job will be priced: by CSI division, by floor, by area or by unit type.
- Add what the model leaves out. See the next section.
- Price it. Material at local prices with tax, labor hours at the local wage, equipment, then overhead and profit.
What a model never includes
Even a good model is a picture of the finished building, not a list of everything it takes to build it. These still come from the estimator:
- Waste and laps: board and roofing cut-offs, wire slack at boxes and panels, concrete over-pour.
- Small parts: fasteners, fittings, hangers, straps, connectors and sealants, unless they were modeled.
- Hidden scope: backing and blocking, firestopping, sleeves and access panels.
- Temporary work: shoring, scaffolds, lifts, temporary power and protection.
- Labor: a model has quantities, not hours. Hours come from production rates and the crew.
- Everything in the specs and notes: finish levels, coats, test requirements and allowances that are written, not drawn.
Level of development: can you take off from this model?
Models are built to different levels of detail. The BIMForum Level of Development (LOD) Specification describes them. At LOD 100 and 200, an element is a placeholder or a generic system: useful for design, not for counting. At LOD 300, the specification says the quantity, size, shape, location and orientation of the element can be measured directly from the model. That is the level a takeoff needs. If parts of a model are below it, measure those parts from the sheets.
Terms you will hear
- BIM (building information modeling): a model whose objects carry information, such as type, size and material, not just shape.
- QTO (quantity takeoff): the list of quantities, from sheets or from a model.
- LOD (level of development): how fully an element is modeled, from LOD 100 to LOD 400 in the BIMForum specification.
- 4D and 5D: a model linked to the schedule (4D) or to cost (5D).
- Clash: two elements that occupy the same space, such as a duct through a beam.
When a 3D takeoff is worth it
A 3D takeoff pays off whenever you need to trust a quantity: tall walls and sloped roofs, buildings with many unit types, jobs with a lot of MEP, and bids your GC or owner will question. On a simple job, a careful 2D takeoff is enough. For how the two compare, read 3D takeoff vs. 2D takeoff.
How BidMe handles 3D takeoffs
BidMe builds every estimate in 3D from your PDF plans, trade by trade, and takes the quantities from that model. You open it in your dashboard, point at any item to see its quantity and the sheet it came from, and change any number. See our 3D estimating and takeoffs page, or pricing: residential estimates start at $199 and commercial at $399.
Questions contractors ask
Is a 3D takeoff the same as a BIM takeoff?
Mostly. A BIM takeoff is a 3D takeoff from a BIM model, usually supplied by the design team. A 3D takeoff can also come from a model built from 2D PDF plans for estimating.
Is a 3D takeoff more accurate than a 2D takeoff?
It can be, because heights and slopes are real and overlaps show. But a model is only as good as how it was built, so it still has to be checked against the sheets.
Do I need Revit or BIM software to use a 3D takeoff?
Not if someone else builds the model and gives you the quantities in a form you can read. BidMe estimates open in the browser, with an Excel workbook, so no modeling software is needed.
Does a 3D takeoff include labor?
No. A model gives quantities. Labor hours come from production rates and the wage for the area, added when the takeoff is priced.